Awarded to:
 
JW Kelso, November 2015

Construction began November 11, 2015; no access to the park or boat ramp.

Status Update:

-Boat Ramp: Pier has been removed and sheet pilings are being installed.
Estimated date for completion: Late Spring 2016

-Lee and Joe Jamail Bay Park: construction has not begun
Estimated date for completion: Late Summer 2016




-Pedestrian Bridge: construction has not begun