​Jack Brooks Road Construction

 

Awarded to:
Lucas Construction, November 2015

Construction Phases:
Construction began December 8, 2015.
Phase I: FM-2004 entrance to three-way stop; the entrance to the park from FM 2004 is currently closed. Please use the park entrance off State Highway 6.
COMPLETED JANUARY 2016
Phase II: Veterans Recreation Area to Highlands Recreation Area; COMPLETED MARCH 2016
Phase III: Highlands Recreation Area to the four-way stop at Jack Brooks Road (near the archery range/flying field intersection): COMPLETED
Phase IV: Four-way stop at Jack Brooks Road (near the archery range/flying field intersection) to the bridge/diversionary canal: COMPLETED

THE PROJECT IS NOW COMPLETE; PLEASE ENJOY THE PARK AND DRIVE SAFE!